Progress Update:  August 28th thru September 8th

Two Week Project Outlook:

Week of August 28th – September 1st:

  • Fine grading the roadway on Brux Road.
  • Asphalt paving the roadway on Brux Road.
  • Fine grading the roadway on Nottingham Road.
  • Asphalt paving the roadway on Nottingham Road.
  • Begin ditch grading and culvert replacement along Brookhaven Drive and Brookhaven Court.
  • Pulverize existing roadway along Brookhaven Drive and Brookhaven Court.
  • Begin roadway excavation along Brookhaven Drive and Brookhaven Court.
  • Begin ditch grading and culvert replacement on Carols Lane.
  • Install gravel shoulder in the Red Tail Lane, Red Tail Court, Tree Line Court and Falcon Court areas.

Week of Week of September 4th – September 8th:

  • Continue roadway excavation along Brookhaven Drive and Brookhaven Court.
  • Landscape restoration along Brookhaven Drive and Brookhaven Court.
  • Pulverize existing roadway on Carols Lane.