2017 Roadway Construction Project (9/11/17 - 9/22/17)

2017 Roadway Construction Project (9/11/17 - 9/22/17)

09/09/2017

Two Week Project Outlook:

Week of September 11th - September 15th:
  • Landscape restoration along new shoulder and touch up areas in the Red Tail Lane, Red Tail Court, Tree Line Court, Falcon Court, Brux Road and Nottingham Road areas.
  • Finish ditch grading and culvert replacement along Brookhaven Drive and Brookhaven Court.
  • Pulverize existing roadway along Brookhaven Drive and Brookhaven Court.
  • Continue roadway excavation along Brookhaven Drive and Brookhaven Court.
  • Pour concrete curb and gutter on Brookhaven Court.
  • Continue ditch grading and culvert replacement on Carols Lane.
  • Pulverize existing roadway on Carols Lane.
  • Pour concrete curb and gutter on Carols Lane.
  • Begin roadway excavation on Carols Lane.

Week of Week of September 18th - September 22nd:

  • Finish roadway excavation along Brookhaven Drive and Brookhaven Court.
  • Begin fine grading along Brookhaven Drive and Brookhaven Court.
  • Finish roadway excavation on Carols Lane.
  • Begin fine grading on Carols Lane,

REMINDER: Upon completion of each area, Cedar will be removing all survey stakes in your yards and the Contractor will be removing all underground utility locate flags