2017 Roadway Construction Project (8/21/17 - 8/25/17)
2017 Roadway Construction Project (8/21/17 - 8/25/17)
08/21/2017
Week of Week of August 21st - August 25th:
- Fine grading the roadway in the Red Tail Lane, Red Tail Court, Tree Line Court and Falcon Court areas.
- Asphalt paving in the Red Tail Lane, Red Tail Court, Tree Line Court and Falcon Court areas.
- Begin ditch grading and culvert replacement along Brookhaven Drive and Brookhaven Court.
- Begin roadway excavation on Brux Road.
- Begin restoration along affected ditches along Brux Road.
Begin ditch grading and culvert replacement on Carols Lane.